| June |
» |
NSC
Critical Design
Review |
| |
» |
NSC
Propulsion System
selected (letter
contract) |
| |
» |
USCGC
METOMPKIN (#2)
arrived for conversion
to 123’
|
| May |
» |
SRP
Critical Design
Review |
| |
» |
MPA
Analysis complete;
(CASA 235-300M)
selection confirmed |
| |
» |
Release
contract for
conversion of
123’ Patrol
Boats #2 and
#3 |
| April |
» |
Maritime
Patrol Aircraft
(MPA) Preliminary
Design Review |
| |
» |
VUAV
Preliminary Design
Review |
| March |
» |
NSC
Preliminary Design
Review |
| |
» |
NSC
Long Lead materials
delivery task
order released |
| |
» |
Deliver
Prototype Short
Range Prosecutor
(SRP) (Zodiac) |
| |
» |
Logistics
Information Management
System (LIMS)
Strategic Readiness
Review |
| February |
» |
USCGC
MATAGORDA arrived
for conversion
to 123’
– 02/ 2003 |
| |
» |
Integrated
Baseline Reviews
(CLIN audits)
– 12/ 2002,
February, March,
June 2003 |
| |
» |
HITRON
(AgustaWestland)
lease signed
under Deepwater |
| |
» |
VUAV
(BellHelicopter
Textron) concept
confirmed |
| January |
» |
123’
Patrol Boat Production
Readiness Review |
| |
» |
System-of-Systems
In-Process Review
– 01/ 2003 |
| |
|
»
2002
| 2003
| 2004
| 2005
|